Old Main Monthly Update graphic

April 2026

Exciting things are happening inside and out at 含羞草研究所鈥檚 historic Old Main! Here鈥檚 a look at the progress made this month:

  • 叠补蝉别尘别苍迟.听The east side framing is now complete, establishing the layout for future rooms and corridors. Crews are actively installing MEPF rough-ins, including mechanical ductwork for HVAC systems, electrical box placement for future power and data, and fire sprinkler piping to meet life-safety requirements. This phase is critical, as these systems are installed behind walls before finishes begin.
  • First Floor.聽Sheetrock (drywall) installation is nearing completion, defining interior walls and ceilings. Next, crews will begin mudding, taping, and sanding joints to create a smooth, paint-ready surface. This step transforms framed spaces into finished rooms and prepares the area for final finishes.
  • Second Floor.聽Painting of the first coat in rooms is nearly complete, marking a major visual milestone. Flooring installation has started, signaling the transition from rough construction to finish work. Once flooring is in place, additional trim and fixtures can follow.
  • Third Floor.聽Framing and door installation are about halfway complete. This includes building wall systems and setting door frames, which establish room layouts and circulation paths throughout the floor.
  • Fourth Floor.聽Final trim-oput is nearly complete, including installation of outlets, switches, and lighting fixtures. This is one of the last steps before spaces are fully functional and ready for occupancy.
  • Exterior.聽The north entry stone installation is complete, giving a finished look to one of the building's primary access points and enhancing both durability and appearance.

Seeing these updates come together month by month is incredibly rewarding. Old Main is well on its way to a bright new chapter. Stay tuned for more progress ahead!

blog divider.jpg

Click here to see the April 2026 update.

north entry 04-2-26.jpg

North Entry.聽Stonework at the north entry is complete. A final cleaning will remove grout haze and bring out the full color and detail of the stone.

Fourth Floor 04-2026.jpg

Second Floor.聽Walls have been sanded and the first coat of paint has been applied. This allows follow-on trades to begin installing finishes like trip, fixtures, and casework.

Theater sound booth 04-2026.jpg

Theater Sound Booth. Framing is complete. This space will house audio and lighting controls, serving as the operational hub for performances and events.